Rack assembly
-
Pallet racking, Neupack
Typical racking installation for high storage. It required using of appropriate equipment and a number of montage teams because of high (16 metres) and heavy (230 kg) frames. There were 17550 pallet places installed and 900 frames. The work quality was monitored by the surveyor.
-
Pallet shuttles, WAWEL
A large block of pallet shuttles with conventional pallet racking around – 3 620 pallet places on pallet shuttles, 500 pallet places in pallet rackings, 4 separate zones. The work done in the first phase of the whole investment, what caused difficult work environment and we were given over the worksite in phases. The consistent verification […]
-
Miniload, BIA
Investment Miniload individually for the customer design – 632 pallet places, all fencing with wire mesh, two-column stacker crane, height 8 meters. As at all our installations, we had to work with precision and using high quality measuring devices. The work done in two phases. We had to cooperate with the warehouse automation firm.
-
Pallet rackings and mezzanine, GEODIS
Storage system consisting of conventional pallet racking and a big span mezzanine – 17 400 pallet places, 11 400 rackings, height of the racking 9 meters, 1200 m2 floor on mezzanine. All the works had to be finished in 5 weeks due to customer’s deliveries. To satisfy the customer and fo finish the project we […]
-
Self-supporting warehouse in Israel
Pierwsza na świecie prototypowa konstrukcja magazynu samonośnego o wysokości 33 m i pojemności 36 tys. miejsc paletowych. Zaadaptowana na chłodnie oraz mroźnie do przechowywania standardowych palet EUR. Magazyn obsługiwany przez 6 układnic. Projekt wymagający wypracowania z naszej strony nowego modelu montażowego oraz szeroko zakrojonej współpracy z partnerami z Bliskiego Wschodu. Struktura regałowa stanowi tylko część […]
-
SANDOZ SA self-supporting warehouse with warehouse automation solutions
26 m high self-supporting warehouse, net volume 53,487 m3, total capacity of 14,304 pallet positions, designed for standard euro pallets, served by 220 automatic devices. The project is highly automated. The entire racking system is served by 3 storage and retrieval machines, 24.5 m tall each. The remaining automatic infrastructure elements are located on three […]
-
Ceramika Paradyż self-supporting warehouse with warehouse automation solutions
Self-supporting warehouse with an internal volume of 83,597 m3 and height of 24.5 m with hip roof, total capacity of 20,256 pallet positions, designed for heavy euro pallets. Very large pre-storage zone with automation solutions and automatic internal transport (monorail). The entire racking system is served by 8 storage and retrieval machines, 22.5 m tall […]
-
Miniload SIEMENS
The Miniload system at the Siemens manufacturing facility in Germany is composed of 3 blocks 335 m3 each with a 6-metre S/R machine. Each block serves approx. 900 boxes. Installation work had to be preceded by disassembly of the old machines within a very confined space. The assembly required very high precision. The racks have […]
-
Racks arranged in rows, Stokrotka
Installation of the most typical type of pallet racking – racks arranged in rows. Implementation was divided into three stages to enable the work of other contractors. The project required very fast assembly work which necessitated the involvement of a large number of experienced employees (at times more than 20 installers working on various worksites).
-
Landena, AUT
Movirack racks with 16 mobile bases (60 m guides, approx. 700 pallet positions). The bases enable to reduce the space required for operation of the system to the necessary minimum. The project was implemented in two stages – fitting of the guide rails and assembly of the mobile bases and of the racks. The installation […]
-
Drive-in rack, Coca-Cola ARE
First project implemented in the Middle East – assembly of drive-in racks (2 blocks, 11m high frames, 2,500 pallet positions). A culture clash that significantly broadened MAXIREM horizons. Good organisation including for instance the dispatch of the necessary equipment to the target destination was needed already before our departure. The project required close collaboration with […]