MEDIA EXPERT PL
DETAILS
Location:Łódź
Implementation:May 2024 - July 2024
DESCRIPTION
Relocation of the Shuttle rack system, moving racks with a total capacity of 10,000 pallet spaces. Timeliness was crucial, as the project needed to be synchronized with the transfer of the client’s entire stored inventory. Fortunately, the project was completed in even less time than originally planned.
Shuttle racks / Mediaekspert / 10,000 pallet spaces; dismantling + installation; completion time 6 weeks; rack height 8m; installation volume 13,300 m³ / Łódź / May 2024 – July 2024